Chandrayaan-3 Lander Vikram has landed successfully on the surface of the Moon, on 23 August 2023, at 18:04 Hrs (IST).

Now let us have a look at the journey of the India’s Historic moon mission Chandrayaan-3, from launching to landing on moon.

August 24, 2023

Chandrayaan-3 ROVER: Made in India. Made for the MOON! The Ch-3 Rover ramped down from the Lander and India took a walk on the moon ! More updates soon.

August 23, 2023

‘I reached my destination and you too!’: Chandrayaan-3
Chandrayaan-3 has successfully soft-landed on the moon. Congratulations, India!

chandrayaan3

August 22, 2023

The mission is on schedule. Systems are undergoing regular checks. Smooth sailing is continuing. The Mission Operations Complex (MOX) is buzzed with energy & excitement!

August 20, 2023

The Lander Module is in 25 km x 134 km orbit. Powered descent is expected to commence on August 23, 2023, around 1745 Hrs. IST

August 19, 2023

The Lander Module is in 113 km x 157 km orbit around the moon. Second de-boosting is planned for August 20, 2023

Chandrayaan-3 Mission
Chandrayaan 3 Photo Credit: ISRO

August 17, 2023

Lander Module is successfully separated from the Propulsion Module. Deboosting planned for August 18, 2023

August 16, 2023

The spacecraft is in an orbit of 153 km x 163 km after the firing on August 16, 2023

August 14, 2023

The mission is in the orbit circularisation phase. The spacecraft is in 151 km x 179 km orbit

Chandrayaan-3 Mission
Chandrayaan 3 Photo Credit: ISRO

August 09, 2023

Chandrayaan-3’s orbit is reduced to 174 km x 1437 km following a manuevre performed on August 9, 2023

August 06, 2023

LBN#2 is successfully completed. The spacecarft is in 170 km x 4313 km orbit around the moon

Chandrayaan-3 Video: The Moon, as viewed by Chandrayaan-3 during Lunar Orbit Insertion

August 05, 2023

Chandrayaan-3 is successfully inserted into the lunar orbit. The orbit achieved is 164 km x 18074 km, as intended.

August 01, 2023

The spacecraft is inserted into the translunar orbit. The orbit achieved is 288 km x 369328 km. Lunar-Orbit Insertion (LOI) is planned for Aug 5, 2023.

July 25, 2023

Orbit-raising maneuver performed on July 25, 2023. Next firing (TransLunar Injection), is planned for August 1, 2023.

July 22, 2023

The fourth orbit-raising maneuver (Earth-bound perigee firing) is completed. The spacecraft is now in a 71351 km x 233 km orbit.

July 17, 2023

The second orbit-raising maneuver performed. The spacecraft is now in 41603 km x 226 km orbit.

July 15, 2023

The first orbit-raising maneuver (Earthbound firing-1) is successfully performed at ISTRAC/ISRO, Bengaluru. Spacecraft is now in 41762 km x 173 km orbit.

Chandrayaan-3 Mission
Chandrayaan 3 launching , Photo Credit: ISRO

July 14, 2023

LVM3 M4 vehicle successfully launched Chandrayaan-3 into orbit. Chandrayaan-3, in its precise orbit, has begun its journey to the Moon. Health of the Spacecraft is normal.

July 11, 2023

The ‘Launch Rehearsal’ simulating the entire launch preparation and process lasting 24 hours has been concluded.

July 07, 2023

Vehicle electrical tests completed.